www.uraless.comOHTL 500 kV "Kurgan-Kozyrevo" will make possible exchange of electrical energy between the power grids of Siberia and Urals and increase carrying capacity of overall electrical transmission between Siberia and Ciscaucasian Russia.

OHTL 500 kV “Kurgan – Kozyrevo”

OHTL 500 kV "Kurgan - Kozyrevo"

 Customer - the JSC "FSK (Federal Power Networks Company) UES - MES (Interconnecting Power Networks) of Urals"

Erection of OHTL 500 kV "Kurgan-Kozyrevo" will allow to transfer through the substation "Kozyrevo" to the Chelyabinsk power grid 350-650 MW of power from the Tyumen power grid and Unified Power Grids of Siberia.

OHTL 500 kV "Kurgan-Kozyrevo" will improve connection between different power grids. Modern equipment of the substation 500 kV "Kurgan" in very unlikely case of fault in one of the sections of the power grids will make possible to repair it without affecting other sections and substations of the grids.

OHTL 500 kV "Kurgan-Kozyrevo" will make possible exchange of electrical energy between the power grids of Siberia and Urals and increase carrying capacity of overall electrical transmission between Siberia and Ciscaucasian Russia.

Project comprises:

1. C & E of OHTL 500 kV Kurgan - Kozyrevo - 280 km;

2. Reconstruction and expansion of Substation 500 kV "Kozyrevo";

3. Reconstruction and expansion of Substation 500 kV "Kurgan";

4. Erection of FOCL between the substations "Kurgan" and "Kozyrevo".


Ural Power Engineering Construction Company, construction and erection of substations, FOCL, overhead power transmission lines